Plans have been submitted for a flood alleviation scheme in Byron Recreation Ground, with documents showing the project could cost anywhere “between £2m and £100m” .
The application, submitted by Harrow Council, is currently under consideration and forms part of wider proposals to improve the park while reducing flood risk in surrounding areas.
According to the planning documents, the scheme would include “the construction of an underground storage tank (east side of the park) and a wetland on the west side of the park” . The system is designed to manage heavy rainfall by storing excess water and releasing it slowly.

The application states that “the scheme proposes diverting the surface water from the Thames Water system into the underground storage tank during the peak flooding events”, with a network of pipes connecting the tank and wetland to regulate water levels.
On its website, Harrow Council says the project is being developed in response to flooding affecting parts of Kenton West, Marlborough and Wealdstone in recent years. The council says the scheme will help reduce pressure on the drainage system during heavy rainfall and protect nearby homes, roads and businesses.
The council also says the system will deal with rainwater only and “will not be connected to the sewage system”, while the wetland area is expected to support wildlife and improve the park’s natural environment.
Technical drawings submitted with the application show the project would involve a network of underground pipes, inspection chambers and flow control structures across the park, along with a newly created wetland area. Landscaping plans indicate that some areas of grass would be replaced or reinforced, and some trees may be removed as part of the works.
The scheme forms part of a wider ambition to improve Byron Recreation Ground, with the council aiming for the park to achieve Green Flag status. Other proposed improvements include a new playground, upgraded footpaths and improved entrances.
However, the plans have also prompted concern locally. One resident, posting on social media, said they were worried the scheme could “only in the end move some flood water from one place to another, at great expense, and put as risk properties like mine that border the park.”

The application does not provide a confirmed overall cost beyond the broad estimate, and it is not yet clear what the final budget will be or how the project will be funded.
Subject to approval, the council says construction could begin in late 2026 or early 2027 and is expected to take around 9 to 12 months. Planning documents suggest a construction period running from January 2027 to November 2027.
Harrow Council have been contacted for comments but did not reply ahead of publication.
Get Harrow’s news in your inbox
Enjoyed this story? Join our free newsletter for the latest local news, what’s on and community stories from across Harrow.

Chris Mitchell is the founder and editor of Harrow Online, Harrow’s leading local news platform.
He launched Harrow Online in 2010 as a Facebook page sharing local news and information. Since then, it has grown into a trusted source for breaking news, crime, council decisions, planning, transport, business and community stories across the borough.
Harrow Online reaches hundreds of thousands of readers each month and has a social media audience of more than 200,000 followers.
For news tips, press releases or enquiries, contact Chris at info@harrowonline.org.